Construction work for water and sewage pipelines | Tenderlake

Construction work for water and sewage pipelines

Contract Value:
-
Notice Type:
Contract Notice
Published Date:
04 December 2019
Closing Date:
08 January 2020
Location(s):
PL416 Kaliski (PL Poland/POLSKA)
Description:
Construction of sanitary sewage system along with drainage and pumping stations in Szklarka Mielęcka and Borek Mielęcki, commune Kępno

1. The subject of the contract is the execution of construction works related to the construction of gravity and pressure sanitary sewage system with connections and pumping stations in Borek Mielęcki and Szklarka Mielęcka, commune Kępno with a total length of approx. 5.87 km and making a passage under the national road S8 together with demolition and reconstruction of road surfaces related to the construction of the sewage network in question.

2. Due to the change in the decision of the Poviat Road Administration in Kępno of 30.9.2019, and the annex to the project documentation, the Employer requires that the Contractor perform a trenchless sewer system, and in places where there is no such possibility - the trench method.

A detailed description of the subject of the contract is included in Part III of the ToR - Description of the subject of the contract

1. The subject of the contract is the execution of construction works related to the construction of gravity and pressure sanitary sewage system with connections and pumping stations in Borek Mielęcki and Szklarka Mielęcka, commune Kępno and making the transition under the S8 national road, covering in its scope:

a) Construction of sanitary sewage system, including:

- gravity sewage system made of PE 200 SDR 17 RC pipes with a total length of approx. 3.44 km,

- discharge sewage system made of PE 160 pipes - with a total length of approx. 1.17 km,

- discharge sewage system made of PE 125 pipes - with a total length of approx. 0.56 km,

- discharge sewage system made of PE 110 pipes - with a total length of approx. 0.04 km,

- discharge sewage system made of PE 90 pipes - with a total length of approx. 0.03 km,

- sanitary drains made of PVC pipes 160 - 94 pieces, total length 0.63 km,

- polymer concrete sewage pumping station, together with the power supply installation - 5 sets,

- demolition and reconstruction of road surfaces related to the construction of the sewage network in question.

Due to the change in the decision of the Poviat Road Administration in Kępno of 30/09/2019, and the annex to the project documentation, the Employer requires that the Contractor perform a trenchless sewer system, and in places where there is no such possibility - the trench method.

2. The Contractor should also include the following scope of works in the price of the offer

And activities included in the implementation of the contract:

a) organizing the back-up facilities and the construction site together with the OHS and fire safety measures,

b) costs of full geodetic service, including costs of performing geodetic as-built inventory,

c) costs of establishing and performing archaeological supervision over construction works in order to carry out the necessary archaeological and security documentation works,

d) costs of maintaining the construction site, including utilities,

e) development and implementation (execution and assembly) of temporary traffic organization for the duration of construction works, and disassembly of the marking after completion of works, as well as obtaining the necessary permits to occupy the road lane and pay the required fees in this respect,

f) carry out all tests, checks and acceptances provided for in the technical conditions for the acceptance of construction and assembly works

And installation and described in SST,

g) technical coordination and supervision (employment of the Site Manager).

h) all costs, including costs of supervision over the implementation of works resulting from

Industry agreements (including collisions with the gas pipeline and teletechnical networks),

i) costs related to the removal of excess material from the cutter (so-called destruct) and material from the demolition of cobblestone to the place indicated by the Ordering Party at a distance of up to 15 km

j) insurance policy for all construction risks (CAR / EAR) in accordance with the conditions specified by the Employer in Annex 1A to the ToR, in Part II of the ToR - Model contract on public procurement and in Chapter 18 of the General Conditions of the Contract

k) photographic documentation of conducted works, especially disappearing works,

l) performing all activities required by law necessary to obtain an occupancy permit,

m) performance of the required warranty inspections during the warranty and guarantee period.

3. The Contractor is obliged to secure the roads leading to the construction site against damage caused by the means of transport of the Contractor or its Subcontractors.

The Employer requires that people who perform activities directly related to the performance of works, i.e. manual workers were employed under an employment contract.

A detailed description of the subject of the contract and general requirements for the execution of works and implementation of the task are contained in Part I of the ToR - IDW and part III of the ToR - Description of the Object of the Contract.

Download full details as .pdf
The Buyer:
Wodociągi Kępińskie Sp. z o.o.
CPV Code(s):
45231300 - Construction work for water and sewage pipelines