Roof insulation work | Tenderlake

Roof insulation work

Contract Value:
-
Notice Type:
Contract Notice
Published Date:
08 July 2019
Closing Date:
14 August 2019
Location(s):
DE25C Weißenburg-Gunzenhausen (DE Germany/DEUTSCHLAND)
Description:
New construction of a quadruple sports hall with multipurpose use for roof sealing work

The new quadruple sports hall with multi-purpose use is located at the school center on the Hagenau in Weissenburg in Bavaria. The 2- to 3-storey building will be developed on 2 levels using the natural topography. The representative entrance front in the north provides direct access to the quadruple sports hall on the ground floor. The foundation is conventional as a flat foundation, consisting of a reinforced base plate d = mind. 50 cm. The sports hall is a solid construction with a wooden roof structure. Massive reinforced concrete slabs (d = 20-30 cm), some with joists, coverings and wall-like girders, rest on reinforced concrete walls and / or reinforced concrete columns. The vertical load transfer takes place essentially over the columns and walls to the foundations. The main girders of the roof construction are constructed as a wooden roof structure made of laminated beams and wooden sand bearing boards with acoustic requirements. The roof structure consists of vapor barrier, thermal insulation and plastic film. The stairs consist of prefabricated reinforced concrete elements. The reinforced concrete outer walls, partially filled inside, are clad on the outside with a facade cladding, the northern reinforced concrete outer wall receives a composite thermal insulation system. Window openings are designed as a glass facade with a mullion / transom construction. Reinforced concrete inner walls (d = 20-40 cm, bearing) are partially filled and provided with a paint. Non-load-bearing interior walls are designed as plasterboard walls.

- Elastumerbitumen welding path welded over the entire surface - approx. 1 040 m 2 .

- Thermal insulation WLG 037 W (m 2 K) d = 140 mm - approx. 1 680 m 2 .

- Fallow insulation WLG 037 W (m 2 K) d = 120 to 275 mm approx. 815 m 2 .

- Attic abyss A2-s1, 30 mm, b = 42 to 60 cm-approx. 278 m,

- Flexible polyolefins plastic roof track d = 2.0 mm - approx. 2,840 m 2 .

- roof drainage main / emergency drainage DN 70-34 pieces,

- Dome light 2-layer glass 120 x 120 cm - 7 pieces,

- Skylight 2-layer glass 120 x 120 cm RWA - 2 pieces,

- Skylight 2-layer glass 100 x 300 cm RWA - 12 pieces,

- Safety system system supports - 29 pieces,

- rope safety with rope glider 8 mm-200 m,

- PSA- 1 piece,

- Overburdened roof overpass aluminum - 2 pieces,

- Flat roof hood / cable entry DN 100 to DN 160-10 pieces,

- movement joints - 154 m.

Download full details as .pdf
The Buyer:
Stadt Weißenburg i. Bay.
CPV Code(s):
45261410 - Roof insulation work