The existing outdoor pool in the Salinental valley will be expanded by the new construction of the indoor pool in order to ensure not only the wellness thermal baths but also the offer of the city of Bad Kreuznach in the form of a sports and family pool.
For the new construction, the existing outdoor pool building with supply and changing area and the technical building will be dismantled and replaced by the planned building.
This new building will include the entrance, changing and shower area and integrate the technology for the outdoor pool area. At the same time, structural and technical measures are being taken to sustainably maintain the existing functionality of the outdoor pool and at the same time to increase its attractiveness. In addition, a new children's pool is being built, which can be assigned to both bath areas.
- GFA: 3 950 m
- BRI: 18 867 m
- Swimming pool water surface: 2,300 m
- Water surface of the indoor pool: 539 m
Waterproofing and tiling work:
- Seal floor and wall surfaces approx. 2 240 m
- Sealing of rising components approx. 800 m,
- capillary-breaking 2-component epoxy resin potting approx. 135 m,
- Building board made of extruded polystyrene hard foam as a tile carrier approx. 420 m
- Floor tiles generally approx. 1,335 m
- Wall tiles generally approx. 810 m
- stair floor covering approx. 85 m,
- Floor tiles of the paddling pool approx. 45 m
- Wall covering approx. 20 m
- Special stones approx. 26 m.