The subject of the contract is the development of project documentation divided into three tasks:
Task 1 – Extension of Kardynała Kominka Street with car parks
Task 2 – Construction of a connector between Kominka Street and Orzepowicka Street
Task 3 – Reconstruction of the intersection of Poligonowa-Rycerska streets
Task 1 – Extension of Kardynała Kominka Street with car parksThe subject of the contract is the development of design documentation for the task: Extension of Kardynała Kominka Street with parking lots.
Design assumptions for task 1:
- roadway with nave bituminous (KR3),
- parking spaces along the roadway,
- sidewalk and path for bicycles or path for pedestrians and bicycles,
- adaptation of the existing traffic lights at the intersection with Budowlanych Street (new controller, detection, signals for cyclists),
- LED road lighting, aluminum poles,
- storm water drainage (checking the condition of the existing sewage system along with the reconstruction/extension project),
- reconstruction of conflicting underground utilities and above-ground networks,
- preparation of a two-variant concept together with public consultations in accordance with the Scheme of preliminary design works and public consultations (attached to the SWZ).
The detailed scope is specified in the SWZ with annexes
Task 2 – Construction of a connector between Kominka Street and Orzepowicka StreetThe subject of the contract is the development of design documentation for the task: Construction of the connector of Kominka Street with Orzepowicka Street.
Design assumptions for task 2:
- roadway with nave bituminous (KR3), road connector with a pedestrian and bicycle path between Kominka Street and the existing parking lot,
- roadway with nave bituminous (KR3), road connector with a width of 4 m on the section from the parking lot to Orzepowicka street,
- solutions for bicycle traffic,
- LED road lighting, aluminum poles,
- storm water drainage system – partly new, partly reconstruction of the existing one,
- reconstruction of conflicting underground utilities and above-ground networks,
- implementation of the concept of the road system.
The detailed scope is specified in the SWZ with annexes
Task 3 – Reconstruction of the intersection of Poligonowa-Rycerska streetsThe subject of the contract is the development of design documentation for the task: Reconstruction of the intersection of Poligonowa-Rycerska streets.
Design assumptions for task 3:
- roadway with nave bituminous (KR4),
- solutions for bicycle traffic,
- LED road lighting, aluminum poles,
- rainwater drainage,
- reconstruction of conflicting underground utilities and above-ground networks,
- The intersection is to be relocated to the east.
The City of Rybnik is in the process of carrying out the procedure of changing the City border in the vicinity of the investment in question.
The detailed scope is specified in the SWZ with annexes