Engineering services for the Murgenthal/Vordemwald IO/AO project; K 303, rehabilitation of Landstrasse as overall manager, specialist planner and site manager.
The country road K 303 is to be renovated in a length of 3'420m. The proportion in urban areas is around 450m. In addition to the road construction work, a new road drainage pipe is being built in the city centre. The resulting road water is now fed into a receiving water via a retention filter basin. The road width remains more or less in stock. It is only widened with 0.75m wide banquets each.
On behalf of the following project phases, the services for the following project phases must be provided in accordance with SIA 103:
-33 Approval procedure
-41 Call for tenders, comparison of offers and tender applications
-51 Execution project
-52 execution
-53 Commissioning, completion
Engineering services for the Murgenthal/Vordemwald IO/AO project; K 303, rehabilitation of Landstrasse as overall manager, specialist planner and site manager.
The country road K 303 is to be renovated in a length of 3'420m. The proportion in urban areas is around 450m. In addition to the road construction work, a new road drainage pipe is being built in the city centre. The resulting road water is now fed into a receiving water via a retention filter basin. The road width remains more or less in stock. It is only widened with 0.75m wide banquets each.
On behalf of the following project phases, the services for the following project phases must be provided in accordance with SIA 103:
-33 Approval procedure
-41 Call for tenders, comparison of offers and tender applications
-51 Execution project
-52 execution
-53 Commissioning, completion