- Delivery and checking of the transferred component lists, with system data, electr. Device data, function descriptions (in words), system diagram incl. Designation of the equipment, MSR control scheme, parameters, installation location, review and comparison of the technical system data in the further course of the project;
- Creation of the cable end installation (cable entry) and connection of the device components included in the contractor's scope of order;
- Creation of the hardware configuration and definition of the setting values for target and reference variables, design of the actuators according to the performance data;
- Participation in the planning of the activation procedure for the drives;
- Commissioning and 1-1 tests with the building management system.
Delivery and installation of automation and switchgear.