The tender is made up of 2 lots.
Both lots must be offered.
The most economical bidder for the respective lot will be awarded a lot.
Pollutant remediation in 2 lots:
Lot 1 Police Headquarters 46045 Oberhausen Friedensplatz 2-5:
Dismantling of contaminated components:
- Asbestos-containing flange seals in the basement of the building,
- pipe insulation made of artificial mineral fibers (KMF) throughout the building,
- Asbestos-containing plaster and filler on walls and ceilings, approx. 20,000 m
- Suspended ceilings made of pressed artificial mineral fibers (KMF) approx. 400 m
- Dismantling of non-polluted components,
- Linoleum wall and floor coverings, approx. 7,500 m
- Wall and floor tiles including mortar bed approx. 500 m
Lot 2 Police Headquarters 46145 Oberhausen Wilhelmplatz 2:
Dismantling of contaminated components:
- Asbestos-containing flange seals in the basement of the building,
- pipe insulation made of artificial mineral fibers (KMF) throughout the building,
- PAH-containing sealing coatings in the basement,
- Plaster and fillers containing asbestos on walls and ceilings, approx. 8,000 m
- Asbestos cement ventilation duct approx. 100 m,
- Flat laid mineral wool on the top floor ceiling (KMF) approx. 600 m
- Suspended ceilings made of pressed artificial mineral fibers (KMF) approx. 400 m
Dismantling of non-polluted components
- Linoleum wall and floor coverings, approx. 2,500 m
- Wall and floor tiles including mortar bed approx. 400 m
Dismantling of contaminated components:
- Asbestos-containing flange seals in the basement of the building,
- pipe insulation made of artificial mineral fibers (KMF) throughout the building,
- Asbestos-containing plaster and filler on walls and ceilings, approx. 20,000 m
- Suspended ceilings made of pressed artificial mineral fibers (KMF) approx. 400 m
Dismantling of non-polluted components:
- Linoleum wall and floor coverings, approx. 7,500 m
- Wall and floor tiles including mortar bed approx. 500 m
Dismantling of components containing harmful substances
- Asbestos-containing flange seals in the basement of the building,
- pipe insulation made of artificial mineral fibers (KMF) throughout the building,
- PAH-containing sealing coatings in the basement,
- Plaster and fillers containing asbestos on walls and ceilings, approx. 8,000 m
- Asbestos cement ventilation duct approx. 100 m,
- Flat laid mineral wool on the top floor ceiling (KMF) approx. 600 m
- Suspended ceilings made of pressed artificial mineral fibers (KMF) approx. 400 m
Dismantling of non-polluted components
- Linoleum wall and floor coverings, approx. 2,500 m
- Wall and floor tiles including mortar bed approx. 400 m