The following is the main scope of works of the whole project:
— caisson works: major refurbishment and upgrade works to the spare caisson,
— wear track: replacement of worn steel tracks located on the floor of the lock that the gate slides across,
— outer sill: repair works to the damaged outer sill which causes excessive leakage affecting lock operational duration and success,
— hauling/operating machinery: the hauling/operating machinery in use is the original 1954 equipment and in requirement of complete upgrade/replacement,
— caisson removal/installation: caisson movements, installation and commissioning within lock possession duration.
This is an operational lock entrance to a busy dock, which will need to be out of service for a minimal period while the works are completed.
— caisson works: major refurbishment and upgrade works to the spare caisson,
— wear track: replacement of worn steel tracks located on the floor of the lock that the gate slides across,
— outer sill: repair works to the damaged outer sill which causes excessive leakage affecting lock operational duration and success,
— hauling/operating machinery: the hauling/operating machinery in use is the original 1954 equipment and in requirement of complete upgrade/replacement,
— caisson removal/installation: caisson movements, installation and commissioning within lock possession duration.
This is an operational lock entrance to a busy Dock, which will need to be out of service for a minimal period while the works are completed.