Roadway renewal works as well as ancillary works (repair of pedestrian paths, replacement of curbs, creation of mini-GBA curbs, VRD work, sanitation, development of low-carbon parking...) on 13 service areas of the APRR and AREA networks.
APRR - A71 motorway (3 service areas)LOT 1 concerns 3 service areas located on the A71 motorway; each of these areas will be considered as the object of a (individual) phase of work.
AS of the VOLCANOES of AUVERGNE (PR 354+890 - Direction 1 Bourges>Clermont-Ferrand) - Projected year of work: 2023
As an indication, the main types of work will be as follows:
- Planing the layers of asphalt in place (between -7 cm and -18 cm), for an area of approximately 22,200 m² in total.
- Purge and adjust the underlying shape layer to 30 cm in GNT.
- Manufacture, transport, application of asphalt mixes (in 1 or 2 layers of GB4 0/14 in connection, and BBSG3 0/14 in rolling), for an area of approximately 32,100 m² in total.
- Various VRD works: recovery of gutter type CC1, pedestrian path to create or resume (in green space or concrete), creation of mini-GBA or GSS2 borders, recovery of drain, recovery of VL parking in permeable zone...
AS of the CENTER OF France (Farges-Allichamps/PR 245+990 - Direction 1 Bourges>Clermont-Ferrand) - Forecast year of work: 2024
As an indication, the main types of work will be as follows:
- Planing the layers of asphalt in place (between -5 cm and -12 cm), for an area of approximately 14,900 m² in total.
- Localized purges of roads over 18 cm.
- Manufacture, transport, application of asphalt mixes (in 1 or 2 layers of GB4 0/14 in connection, and BBSG3 0/14 in rolling), for an area of approximately 23,100 m² in total.
- Various VRD works: recovery of gutter type CC1, pedestrian path to create or resume (asphalt or concrete), creation of mini-GBA or GSS2 borders, recovery of drain, ditch cleaning, bridging...
AS of the CENTER OF France (Bruère-Allichamps /PR 246+200 - Direction 2 Clermont-Ferrand>Bourges) - Forecast year of work: 2024
As an indication, the main types of work will be as follows:
- Planing the layers of asphalt in place (between -5 cm and -12 cm), for an area of approximately 21,450 m² in total.
- Localized purges of roads over 18 cm.
- Manufacture, transport, application of asphalt mixes (in 1 or 2 layers of GB4 0/14 in connection, and BBSG3 0/14 in rolling), for an area of approximately 40 500 m² in total.
- Various VRD works: recovery of a gutter type CC1, pedestrian path to create or resume (in asphalt or concrete), creation of mini-GBA or GSS2 borders, recovery of drain, ditch cleaning, bridging, recovery of VL parking in permeable zone...
APRR - A6 North motorway (2 service areas)LOT 2 concerns 2 service areas located on the A6 motorway; each of these areas will be considered as the object of a (individual) phase of work.
AS de LA FERTE (PR 341+700 - Sens 1 Paris>Lyon) - As an indication, the forecast year of work is 2022.
As an indication, the main types of work will be as follows:
- Planing the layers of asphalt in place (between -7 cm and -16 cm), for an area of approximately 18700 m² in total.
- Manufacture, transport, application of asphalt mixes (in 1 or 2 layers of GB4 0/14 in connection, and BBSG3 0/10 or 0/14 in rolling), for an area of approximately 35900 m² in total.
- Various VRD works: recovery of grid and manhole, pedestrian path to resume, creation of mini-GBA or GSS2 borders, clearing of slides, resumption of VL parking in permeable zone...
AS of SAINT-AMBREUIL (PR 341+700 - Direction 2 Lyon>Paris) - As an indication, the forecast year of work is 2022.
As an indication, the main types of work will be as follows:
- Planing the asphalt layers in place (-14 cm), for a total area of approximately 13500 m².
- Manufacture, transport, application of asphalt mixes (in 2 layers of GB4 0/14 in connection, and BBSG3 0/14 in rolling), for an area of approximately 25200 m² in total.
- Various VRD works: recovery of curbs, pedestrian path to create or resume (in concrete), bridging, regaining gaze...
- Resumption of the geometry of the ramp at the entrance to the area: widening of the roads and correction of the profile (earthworks, layers of foundation and bearing...).
APRR - A6 South motorway (2 service areas)LOT 3 concerns 2 service areas located on the A6 motorway; each of these areas will be considered as the object of a (individual) phase of work.
AS of DRACE (PR 407+470 - Sens 1 Paris>Lyon) - As an indication, the forecast year of work is 2022.
As an indication, the main types of work will be as follows:
- Planing the layers of asphalt in place (between -5 cm and -13 cm), for a total area of about 40000 m².
- Localized purges of roads over -21 cm.
- Manufacture, transport, application of asphalt mixes (in 1, 2 or 3 layers of GB4 0/14 in base and in bond, and BBSG3 0/10 or 0/14 in rolling), for an area of approximately 53250 m² in total.
- Various VRD works: recovery of grid, recovery of borders, pedestrian path to be created (in concrete), creation and recovery of mini-GBA curbs, removal of slides, recovery of car parking in permeable zone, development of picnic tables...
AS of TAPONAS (PR 408+400 - Sens 2 Lyon>Paris) - As an indication, the forecast year of work is 2023.
As an indication, the main types of work will be as follows:
- Planing the layers of asphalt in place (between -7 and -17 cm), for an area of approximately 23650 m² in total.
- Localized purges of roads over -19 cm.
- Manufacture, transport, application of asphalt mixes (in 2 layers of EME in base bond, and BBSG3 0/10 or 0/14 in rolling), for an area of approximately 30250 m² in total.
- Various VRD works: recovery of grids, look to create, pedestrian path to create (in concrete), takeover of mini-GBAs, development of picnic tables...
AREA - A43 motorway (6 service areas)LOT 4 concerns 6 service areas located on the A43 motorway; each of these areas will be considered as the object of a (individual) phase of work.
AS of ISLE d'ABEAU SUD (PR 28+287 - Direction 1 Lyon>Chambéry): As an indication, main types of work:
- Planing the layers of asphalt in place (between -8 cm and -13 cm), for an area of approximately 22000 m² in total.
- Manufacture, transport, application of asphalt mixes (in 1 or 2 layers of GB4 0/14 or BBSG 0/10 in connection, and BBSG3 0/10 or 0/14 in rolling), for an area of approximately 40100 m² in total.
- Various VRD works: recovery of grates and borders, creation and recovery of mini-GBA borders, recovery of green spaces, development of picnic tables, earthworks and installation of a sanistation...
AS of L'ISLE d'ABEAU NORD (PR 29+423 - Direction 2 Chambéry > Lyon): As an indication, main types of work:
- Planing the layers of asphalt in place (between -6 cm and -8 cm), for an area of approximately 28400 m² in total.
- Localized purges of roads at -15 cm.
- Manufacture, transport, application of asphalt mixes (in 1 or 2 layers of GB4 0/14 in connection, and BBSG3 0/10 or 0/14 in rolling), for an area of approximately 33400 m² in total.
- Various VRD works: recovery of concrete wedge, recovery of gutter type CC1, recovery of grid and curbs, creation of pedestrian pathways (in concrete), removal of fence, supply and installation of gantries templates, earthworks and installation of a sanistation...
AS of the GRANIER (PR 100+321 - Direction 1 Chambéry>Albertville): As an indication, main types of work:
- Planing the layers of asphalt in place (between -6 cm and -12 cm), for an area of approximately 8600 m² in total.
- Manufacture, transport, application of asphalt mixes (in 1 or 2 layers of BBME 0/10 in connection, and BBSG3 0/10 or 0/14 in rolling), for an area of approximately 11500 m² in total.
- Various VRD works: Creation of slotted gutters, creation of mini-GBA borders and removal of rock blocks, creation of pedestrian pathways (in concrete), installation of J11 beacons, ditch filling and nozzle...
AS of the ABIS (PR 100+418 - Direction 2 Albertville>Chambéry): Indicatively, main types of work:
- Planing the layers of asphalt in place (between -8 cm and -15 cm), for a total area of approximately 16300 m².
- Manufacture, transport, application of asphalt mixes (in 1 or 2 layers of GB 0/14 in connection, and BBSG3 0/14 in rolling), for an area of approximately 30900 m² in total.
- Various VRD works: recovery of edges, creation of mini-GBA edges and removal of rock blocks, filling of ditches and busting, leveling of merlons...
AS of ROMAGNIEU (PR 64+730 - Sens 1 Lyon>Chambéry): As an indication, the main types of work will be as follows:
- Planing the layers of asphalt in place (between -6 cm and -14 cm), for a total area of approximately 6250 m².
- Manufacture, transport, application of asphalt mixes (in 1 or 2 layers of GB 0/14 in connection, and BBSG3 0/14 in rolling), for an area of approximately 12200 m² in total.
- Various VRD works: recovery of curbs and grids, creation of mini-GBA curbs and removal of rock blocks, pedestrian path to be removed, recovery of concrete sidewalks, development of picnic tables...
AS of GUIERS (PR 64+888 - Direction 2 Chambéry>Lyon: Indicatively, main types of work:
- Planing the layers of asphalt in place (between -5 cm and -14 cm), for an area of approximately 12500 m² in total.
- Localized purges of roads over -22 cm.
- Manufacture, transport, application of asphalt mixes (in 1 or 3 layers of GB 0/14 in connection and base, and BBSG3 0/10 or 0/14 in rolling), for an area of approximately 26800 m² in total.
- Various VRD works: recovery of curbs and grids, development of a gutter, recovery of mini-GBA curbs, pedestrian path to create or resume...