The refurbishment of the Altmühlfranken-Gunzenhausen hospital takes place in several phases during ongoing operation. The hospital is divided into 3 main areas, component A, component B and component C in stock. The final stage of the project is to plan all untreated areas in the clinic so that the clinic is completely renovated.
Quantities:
Initial painting on walls: approx. 13 340 m
First coats on ceilings: approx. 2 675 m
First coats on steel frames, 1-leaf doors: 189 pieces.
Performance dates:
BTA, EC
Beginning 27.5.2019
End 28.6.2019
BTA, 3rd floor
Beginning 27.5.2019
End 28.6.2019
BTC, 3 + 4th floor
Beginning 5.8.2019
End 13.9.2019