On Friedrich-List-Platz 2 in 01069 Dresden the new building of the joint head office of DREWAG and ENSO with two high-rise buildings is planned and connects to the City Genter from the south. The construction site borders on Lindenaustrasse in the south. Fritz-Löffler-Str. Is located in the east. with tram tracks and in the west a neighboring property with lower buildings. The new building is planned with two basement levels, the construction pit is approx. 9 m deep. The cubic building, which is staggered in height, encloses a rectangular courtyard with its five lower floors and forms a six and a 13-storey tower on its north and south sides. A building with approx. 27 200 m is created
The list of services includes the services for the delivery and installation of the high-voltage systems.
The following systems are installed in the new main building management of ENSO / DREWAG:
- 2 main building distributions (general network);
- 2 main building distributions (backup network);
- busbar trunking system up to 4,000 A;
- busbar trunking system up to 1 250 A;
- distributors and built-in appliances;
- approx. 5 500 m lines with functional integrity;
- approx. 1 750 m flat cables;
- approx. 79 000 m installation cables up to 5x6 mm²;
- approx. 11 300 m installation lines / cables up to 240qmm;
- approx. 10,000 m installation system for climbing and cable routes;
- approx. 6 100 pieces of installation equipment (switches, sockets, etc.);
- Lighting system with general lighting (approx. 2,800 luminaires) and safety lighting (connection to the NEA).
- Stationary power pack with 800kVA on the 7th floor.