Bildungszentrum Fruerlund, new construction of the daycare center, Flensburg, extended shell, Az. 278/2023.
Bildungszentrum Fruerlund, new construction of the daycare center, Flensburg, extended shell, Az. 278/2023:
Execution period: 02.04.2024 to 18.10.2024
Description of the advertised services:
- construction site equipment
- Technical processing of FT stairs, FT plinth elements, exposed concrete surfaces, construction joints, drainage, etc.
- Earthworks and drainage work with
approx. 1,600 m3 excavated soil excavation pit with removal
approx. 500 m3 excavated soil excavation, lateral storage
approx. 800 tons Disposal of excavated soil according to LAGA Z1.2, Z2, or landfill class I and II
Produce approx. 920 m2 of fine grading
approx. 500 m3 of workspace backfilling with laterally stored material
approx. 500 m3 of workspace backfilling with delivery material
Laying approx. 310 linear metres of drainage pipe, including earthworks
ca. 15 St. Drain-Kontrollschächte DN300
approx. 870 m2 drain layer under soles, d = 15 cm
- Reinforced concrete work with
approx. 870 m2 C25/30 floor slabs with cleanliness layer, perimeter insulation and separating film
approx. 123 m2 formwork of strip and individual foundations, straight and stepped
approx. 19 m3 in-situ concrete C25/30 of the strip and individual foundations
approx. 3,100 m2 formwork of the walls, of which approx. 440 m2 in exposed concrete SB3
approx. 316 m3 of in-situ concrete C25/30 of the walls
approx. 100 m2 formwork of rectangular columns
approx. 10 m3 in-situ concrete C25/30 of the rectangular columns
approx. 485 m2 formwork of the beams and beams, of which approx. 200 m2 in exposed concrete SB3
approx. 160 m3 in-situ concrete C25/30 of the subbeams and overlays
approx. 1,950 m2 formwork of the ceilings, floor heights up to approx. 3.80 m
approx. 430 m3 in-situ concrete C25/30 of the ceilings
approx. 117 m FT plinth elements, h=45 cm, in different lengths
approx. 4 FT stairs, straight with 10-12 gradients approx. 17/29 cm indoors
approx. 2 FT stairs, straight with 11 gradients approx. 17/29 cm outdoors
approx. 156 tons of reinforcement of the in-situ concrete components, B500 S+M (A)
- Masonry work with
approx. 150 m3 load-bearing KS masonry 20/2.0, d = 17.5 cm
approx. 120 m2 load-bearing KS masonry 20/2.0, d = 11.5 cm
- Waterproofing work with thermal insulation
approx. 500 m2 of mineral sealing slurries
ca. 500 m2 Perimeterdämmung XPS35, d=120-160 mm
approx. 117 linear metres of base sealing with EPDM barrier foil
approx. 420 m2 knobs/drainage plate
- Technical trades with
approx. 135 running metres of plastic sewer drainage pipes DN100 and 125, including earthworks
approx. 250 m lightning protection cables made of galvanized strip steel 3.5x30 mm
approx. 385 m lightning protection cables made of V4A round wire, d = 10mm
approx. 415 running metres of DN25 conduits in concrete components