The Protestant Parish of Weinheim is planning to build a parish house with a parish office and a children's day facility on the property at Markusturm, Hainbuchenweg/Birkenweg in 69469 Weinheim.
The contractor's services include the complete earthworks, shell construction and civil engineering work:
- Earthworks (excavation pit, pipe trenches, deep foundation)
- Concrete work (StB floor slab, foundations)
- sealing and insulation work
- Building drainage and technical facilities for supply and disposal of new buildings
Approx. 1500 m³ Excavated soil (excavation pit and pipe trenches) Approx. 300 m³ In-situ concrete (floor slab, foundations) Approx. 150 pieces of full displacement piles Approx. 1200 m² Perimeter insulation 80mm Approx. 60 t Reinforcing steel