In essence, the following services have to be provided:
- Earthworks: Excavation excavation about 6 300 m
- Laying fresh concrete composite foil approx. 2 000 m
- concrete work: floor slabs incl. Formwork approx. 760 m
- Concrete works: walls including shuttering approx. 1 200 m
- Share of white tub (WU concrete incl. Sealing concept) at concrete positions approx. 1 000 m
- Concrete works: Ceilings incl. Formwork approx. 660 m
- Proportion of exposed concrete surfaces on shuttering surfaces approx. 2 200 m
- masonry work: interior walls of sand-lime brick approx. 500 m
- Scaffolding: working and protective scaffolding incl. Storage approx. 2,100 m
- External wall insulation incl. Perimeter insulation approx. 590 m
The Bad Tölz-Wolfratshausen district will build a multiple gymnasium (triple hall) at the Geretsried school center. For this purpose, the master-builders announced here and in the course of the procurement are required (see II. 1.4).