Renovation and extension of the Johann Peter Hebel secondary school -Refurbishment of existing buildings-
-Demolition work (pollutant renovation/shell work)
1st BA East: 26.07.2022 - 22.08.2022 2nd BA West: 01.08.2023 - 04.09.2023 “Renovation of existing buildings” will be carried out in two construction phases:
1st construction phase during the school summer holidays 2022 (28.07.2022 to 10.09.2022) 2nd construction phase during the school summer vacation 2023 (27.07.2022 to 09.09.2023)
Pollutant remediation/structural work:
Dismantling System partitions: 1,250 m² Remove old surfaces (Lino): 1,650 m² Disassembly Screed: 2,000 m² Concrete ceiling dismantling: 11 m² Masonry walls 11.5 m: 34 m²