The new building of the sports hall will be built on the area of the previous sports field at the school between the school building and Waldschmidtstraße.
The building is predominantly a reinforced concrete structure with EIFS. The roof of the sports hall is hipped. The
Roof construction is designed as an explosive device with wooden trusses and steel tension struts. Buildings for
changing rooms, plumbing, technology, equipment and gallery with a green flat roof.
Exterior building dimensions: approx. 38 x 45 m
Building height: approx. 14 m
masses:
ETICS system incl. façade paint approx. 800 m2
Interior plaster approx. 500 m2
Interior walls in rooms paint approx. 2000 m2
Painting ceiling in rooms approx. 210 m2
Acoustic ceiling in the gym paint approx. 1000 m2
Walls in the gym paint about 500 m2
Wooden surface in the outdoor area glaze approx. 200 m2
Indoor floor painting approx. 160 m2
Paint various steel parts such as door frames, railings, etc.
Ausführungszeitraum: 02.02.2023 – 07.07.2023
other CPV codes
45442110-1 Painting work in buildings
45321000-3 thermal insulation work
45410000-4 plastering