New construction of sports hall with canteen Reichenbach - PV system
New sports hall with canteen with an area of approx. 3,500 m² GFA in Reichenbach an der Fils. This includes the necessary work for the PV system.
Main masses for the PV systems:
- Installation of mounting system from 11.09.2023 (after insulation/sealing roof area 1 sports hall); approx. 1 KW
- Installation of PV modules, cable support systems, cable pull from 16.10.2023 (after green roof); approx. 2-3 KW
- Installation of inverters, final assembly until 06.05.2024; approx. 1 KW
- Commissioning until 31.05.2024, after completion of meter cabinet
- Acceptance, removal of defects, instruction until 14.06.2024