District heating supply for Strib, Component and Pipe Delivery, Stage 1-5

Medelfart district heating has been approved by project proposals under the Heat Supply Act on conversion from gas to district heating of the whole Strib and Røjle and Vejlby. The conversion is divided into 5 stages and the present supply of pre-insulated district heating pipes and components for all 5 stages.

All 5 stages include approximately 45 km of main supply lines up to the DN300 and approximately 25 km of connectors.

Connectors for all 5 stages are inserted as an option.

Medelfart district heating has been approved by project proposals under the Heat Supply Act on conversion from gas to district heating of the whole Strib and Røjle and Vejlby. The conversion is divided into 5 stages and the present supply of pre-insulated district heating pipes and components for all 5 stages.

All 5 stages include approximately 45 km of main supply lines up to the DN300 and approximately 25 km of connectors.

Connectors for all 5 stages are inserted as an option.

Download full details as .pdf
The Buyer:
Middelfart Fjernvarme a.m.b.a.
CPV Code(s):
44163120 - Distance-heating pipes