As part of the renovation of House B at the DRK Kamillus Clinic in Asbach, demolition and shell construction work must be carried out in several construction phases while the hospital is running.
As part of the renovation of House B at the DRK Kamillusklinik in Asbach, the following services are to be carried out in several construction phases while the hospital is running:
- dust protection walls;
- Demolition of masonry: 460 m
- Demolition of GK walls 20 m
- Demolition wall tiles: 450 m
- Demolition floor tiles: 95 m
- Demolition of PVC floor coverings: 750 m
- Solve wallpapers: 1 600 m
- Break off 85 frames and doors;
- 550 m
- cancel 60 sanitary objects;
- core drilling;
- wall openings;
- masonry work, small areas;
- precast falls.
The figures are approximate quantities.