Demolition of the prestressed concrete bridge, length 107 m;
Replacement road bridge in steel composite construction over railway tracks and river, length 107 m.
Demolition of the old bridge over the Iller and the railway tracks:
- Dismantling of caps, covering, sealing, railings, bridge equipment,
- Dismantling the stair tower,
- Demolition of the superstructure of the prestressed concrete girder bridge, partly on shoring, partly conventional,
- Demolition of the substructure of reinforced concrete.
Replacement construction of the bridge over the Iller and railway tracks:
- Substructures partly with shallow foundations and partly with deep foundations on large bored piles,
- Superstructure in composite steel construction, single-cell, open hollow box; Lifting with mobile cranes,
- deck slab in in-situ concrete,
- Caps, sealing, covering, railings, bearings, ÜKO, bird protection, corrosion protection, internal earthing.
Accompanying measures:
- production of dams and pre-fillings,
- Construction of construction roads.