Sanitary/ventilation systems for the construction of a residential district with 152 apartments with a total area of approx. 11,000 m² in Stutensee Blankenloch, on the site of the former swimming pool.
The construction site is divided into 2 sub-areas, each with a separate underground car park.
The apartments are arranged in 9 three-four-storey spatially separated buildings with 15 house entrances.
A café is to be integrated on the ground floor of House VII. Due to the high rated water level, a closed excavation pit with construction and soft gel sole is planned.
The overall completion of all apartments is planned by the first quarter of 2024.
The order specifically includes the performance of plumbing/ventilation systems.
Further details are provided in the offer documents.
Plumbing/Ventilation Systems Lot 1 - Section APlumbing/ventilation systems
The call for proposals is divided into two lots
Bidders can bid in individual lots.
The award can take place in individual lots.
Lot 1 - Section A
Drywall pre-wall system for: Part A 99 bathrooms
Washbasins/washdown toilet: part A approx. 130 pieces
Stainless steel line pipe: part A approx. 2,800 m
Multi-layer composite pipe: part A approx. 2,600 m
sewer pipes: part A approx. 2,500 m
Exact information can be found in the course.
Single terms/intermediate deadlines
Monday, 13.06.2022 - Friday, 10.03.2023 Assembly Assembly Lot 1 Sanitary/Ventilation
Monday, 12/12/2022 - Friday, 08.12.2023 Final assembly Lot 1 Plumbing/Ventilation
Plumbing/Ventilation Systems Lot 2 - Section BPlumbing/ventilation systems
The call for proposals is divided into two lots
Bidders can bid in individual lots.
The award can take place in individual lots.
Lot 2 - Section B
Drywall pre-wall system for: Part B 54 bathrooms
Washbasins/wash-down toilet: part B approx. 85 pieces
Stainless steel line pipe: part B approx. 2,000 m
Multi-layer composite pipe: part B c. 1,600 m
sewer pipes: part B approx. 660 m
Exact information can be found in the course.
Single terms/intermediate deadlines
Monday, 13.03.2023 - Friday, 21.07.2023 Assembly Assembly Lot 2 Plumbing/Ventilation
Monday, 03.07.2023 - Friday, 03.11.2023 Final assembly Lot 2 Sanitary/Ventilation