New road bridge SR12 (old)
Buildings
- New construction of 4-span integral bridge structure, total length approx. 65 m:
Excavation pit shoring (sheet pile wall, 5 individual excavation pits):
Spundwandarbeiten: approx. 950 m²
Stahlbetonarbeiten: approx. 850 m³
- Dewatering required for 5 individual excavation pits
(2 x abutments, 3 x pillars)
- Sheet pile wall inlet structure flood protection polder:
Spundwandarbeiten: approx. 400 m²
- Auflockerungsbohrungen vor o.g. Spundwandarbeiten: 2,000 Bohrmeter
Dike, road and path construction work
- Earthworks:
Fill flood protection / road body bypass during construction: approx. 5,000 m³ (delivery material)
- Demolition of asphalt pavement: approx. 650 t
- Road construction (asphalt base and surface course): approx. 1,700 m²
- Road construction (gravel pavement): approx. 830 m³
- Oberbodenarbeiten: approx. 3,000 m³