Lot 09: Plastering work
Part of the building extension
Interior plaster:
- construction site equipment
- Coverage floor area approx. 1400 m2
- Primer approx. 1390 m2
- Spritzbewurf ca. 1390 m2
- Lime-cement plaster 1-layer Q2 approx. 1390 m2
- Execution in Q3 approx. 1000 m2
- Electric slots close approx. 90 m
Sockelputz:
- Reinforcement, reinforcing mortar approx. 165 m2
- Base plaster 3-4 mm with primer approx. 165 m2
- Mineral sealing slurry approx. 135 m2
- Sockelanstrich ca. 165 m2
Part of the existing building
Façade/plinth:
- Construction site equipment, lifting platform
- Dismantle ETICS façade and plinth 8 m2
- Preparatory work on façade and plinth for new ETICS 17 m2
- Waterproofing, perimeter insulation XPS-R, dimpled membrane approx. 3 m2
- Reinforcement, reinforcing mortar approx. 3 m2
- Base plaster with primer approx. 3 m2
- Mineral sealing slurry approx. 3 m2
- Sockelanstrich ca. 3m2
- ETICS with 6 cm rock wool 040 approx. 22 m2
- Colour coating façade approx. 22 m2
- Connection, processing to existing buildings
- Remove plaster layer in the reveal area window approx. 23 m
- ETICS in the area of new window reveal approx. 65 m
- Waste disposal approx. 0.1 t
Interior plaster:
- Floor coverage approx. 180 m2
- Components protect foil approx. 70 m2
- Demolition of interior wall plaster in partial areas approx. 27 m2
- Putzergänzung ca. 27 m2
- Kalkzementputz Leibung ca. 125 m
- Plaster defects approx. 15 pcs
- Plaster on walled openings approx. 10 m2
- Lime cement plaster interior wall masonry 88 m2
- Lime cement plaster wall exposed aggregate concrete approx. 28 m2