Conversion measures on existing buildings of the Hospital Mittweida in the trades flooring work, tiling work, painting work in the context of construction phase B
The district of Mittweida Krankenhaus gGmbH is planning to move from still used premises to other rooms in the existing building as a preparatory measure for the demolition of the existing building House 2. For this purpose, interventions in the area of the TGA are required. As building freedom for these building services interventions, various expansion measures are required in individual rooms of the existing building:
Conversion Of Construction Phase B - Lot 2 Flooring / Tiles / Painter
The following main services are carried out:
- Bodenbelagarbeiten
o approx. 25m² ground sanding and suction
o approx. 70m² surface spatula
a ca. 55m² Linoleum
o ca. 20m² Vinylbelag (Bahnenware)
- tiling
o approx. 55m² wall tiles
- painting
o approx. 90m² protective cover on windows, making and removing doors made of foil
o approx. 240m² ceiling painting with silicate fibre (new and overhaul paint)
o approx. 270m² wall paint (new and overhaul paint)
o ca. 20m² Epoxidharzbeschichtung
- Painting work
o 5 steel enclosing frames of new doors
Time sheets according to construction schedule
Start of construction: 04.10.2022
End of construction: 16.12.2022