Roofing and plumbing work
As part of the renovation and partial conversion of a school building from the 1970s, manufactured in large panel construction, not basement, 4 full floors, as well as a largely free-standing building with a swimming pool system, manufactured in conventional construction, basement, 1 full floor, the following construction services are awarded in public tender:
- Roof waterproofing work (execution 24.04.2023 to 12.07.2023)
The execution of the roof waterproofing work includes:
Dismantling of existing waterproofing of school building House B
- Dismantling sealing bitumen membrane two-layer, approx. 990m2
- Dismantling tar board, glass fleece, HPL plates, polystorol approx. 990m2
- Dismantling slope concrete approx. 290m3
Roof waterproofing school building House B
- Apply vapour barrier horizontally / vertically 1200 m2
- Insulating layer as slope insulation layer 1300 m2
- 2-layer composite waterproofing polymer bitumen membrane 1300 m2
- Fall protection
Roof plumbing school building House B
- Attikaverblechung 150m
- 2 light domes