New construction kbo-Inn-Salzach-Klinikum - Construction of nursing building components C and D
Sheeting work
825 m² Verbauwand Trägerbohlverbau
earthwork
33,000 m³ excavation work
830 m² Aspaltbelag
30,000 m³ floor installation and modelling
20,000 m³ soil improvement with binders
2.100 m³ Oberbodeneinbau
19.000 m² Ansaat
4 pcs shaft DN 1200 T up to 6.5 m
1 pcs shaft DN 1500 T up to 6.5 m
1 pcs crash shaft DN 2500 up to 11.0 m