Extension of the secondary school Mühldorf am Inn
The heat is supplied via a newly built air heat pump system and the existing one. The heating system is planned as a pump hot water heater, as a closed system.
Heizungsarbeiten
approx. 30 m Dismantling pipeline DN 10 to DN 50
1 pcs compact air heat pump
ca. 30 m Nahwärmeleitung Doppelrohr 2x50x4,6
approx. 70 m pipeline made of medium-weight threaded pipe Outer diameter 21.3 mm to 48.3 mm
approx. 900 m pipeline made of stainless steel pipes DVGW GW 541, welded, for drinking water, outer diameter 15 mm to 28 mm
approx. 350 m pipeline made of stainless steel pipes DVGW GW 541, outer diameter 35 mm to 42 mm
approx. 1050 pipe suspension, made of steel, DN 15 to DN 40
ca. 92 St. Stahlröhrenheizkörper
approx. 92 pcs. two-pipe tap block with 3/4"