Thermal rehabilitation of the 1409 Gustave NOBLEMAIRE and 1411 Aimé CESAIRE groups located in CLERMONT FERRAND on behalf of the company AUVERGNE HABITAT.
These renovations take place in an occupied environment and aim to obtain the BBC Renovation label.
They concern the 84 dwellings of the 1409 G.NOBLEMAIRE group and the 8 dwellings of the A.CESAIRE group.
It should be noted that the procedures for consulting contracts vary depending on the lot.
Thus
* The consultation of lots 9/10 - 11 - 12 - 13 - 14 - 18/19/20 - 22/23 - 24/25 is carried out according to a formalised procedure
* The consultation of lots 03 - 04 - 28 is carried out according to an adapted procedure. Lots 03 and 28 will be consulted at a later date.
* The consultation of lot 35 is carried out without prior advertising or competition
Lot VRDThe work programme for this lot is currently under consideration.
Thus, this batch will be the subject of a subsequent consultation which will be carried out according to an adapted procedure
Heating - Sanitary plumbing - VentilationReplacement of VMC units
Boiler replacement
In the 12 vacant units: Replacement or installation of showers, replacement of toilets, sink cabinets, faucets
Additional housing may have to be built during the construction site if they become available (CBPU)
ELECTRICITY - LOW CURRENT TV/TEL/ACCESS CONTROLSecuring all the dwellings as part of the BBC Renovation label + addition of sockets + power supply of electric shutters, removal of Bergman-type distributions, etc.
Installation of LED lights in the common areas
Replacement of exterior lighting in buildings
Refurbishment of access control on the CESAIRE group
Green spacesThe work programme for this lot is currently under consideration.
Thus, this batch will be the subject of a subsequent consultation which will be carried out according to an adapted procedure
ASBESTOSRemoval of PVC flooring with asbestos adhesive on 2 steps
Removal of skirting boards with asbestos glue in the kitchen of a dwelling (vacant)
Removal of joinery with asbestos glazed joints on 1 building (window wells)
The consultation of this lot will be carried out without prior advertising or competition
Big workCareful deconstruction and reconstruction of the balconies of both sites
Removal of chimney flues in the attic of one of the two sites
WOOD TREATMENT / ZINC ROOFINGTreatment of all the structures (17 buildings)
Monitoring of roofs and gutters
Replacement of descents and dolphins
Installation of smoke extraction skylights on one of the two sites
ATTIC INSULATION AND SPRAYED INSULATIONInsulation of the ceilings of the cellars of the 17 buildings
Insulation of the attic of the 17 buildings
Passivation of steels in the cellars of 17 buildings
treatment of facadesExternal thermal insulation (rock wool) of the 17 buildings
Exterior wood furnishingsReplacement of all the joinery of the 17 buildings.
Installation of joinery with electric shutters.
INTERIOR JOINERYInstallation of a Swiss threshold, installation of a handle on the outside of the landing doors, installation of a handle on the door of the technical cupboard
Spot calibration
Vitrification of several parquet floors in the 12 currently vacant apartments.
Additional vitrifications may have to be carried out during the construction site if housing becomes available (CBPU)
LocksmithRemoving, treating and reinstalling all the railings (120 balconies)
Installation of grilles at the level of the window wells of each building
PLASTERING-PAINTING-GLUED FLOORS - EARTHENWARE TILESCommon areas:
Insulation and repair of false ceilings
Creation of partitions in some attics
Units: 12 units are vacant. The latter will be rehabilitated in their entirety. The services in each dwelling vary according to their condition or the type of soil.
Depending on the accommodation, the following services will be carried out: installation of PVC floors, installation of glass cloth with repainting, creation of partitions
Additional housing may have to be built during the construction site if they become available (CBPU)