High and low current installation
In the course of the fire protection and energy renovation of the Bürder Grimm School, the electrical installation is also to be renovated. During the implementation of the Digital Pact, the data network has already been upgraded. The school is a three-storey school with an adjoining gymnasium. The work on the school is divided into two construction phases. The scope of the installation includes:
- preparatory work
- Revision of the NSHV
- New main building distribution
- New sub-distributions 1-6 and small distributors
- Expansion of BMA
- new central safety lighting system
- Revision of the ELA
- Supplementation of the EDP network in the administration
- LED Raumbeleuchtung
- outdoor lighting
- I&C cabling
- Connection of the PV system
- Upgrading of the lightning protection system
- KNX for heating, sun protection, lighting
- Fire protection ducts, routes