Approx. 7,000 m pipeline Approx. 1,500 sqm ventilation duct Approx. 360 m Winding seam pipe 1 x Drinking water distribution cold and warm 1 x Hygiene system 39 x Sanitary ware 17 x Radiators Approx. 830 m² Underfloor heating 2 x Heat pump 1 x Ventilation unit for 12,000 m3/h Start of work: November 2022 Duration of work: 220 working days
Approx. 7,000 m pipeline Approx. 1,500 sqm ventilation duct Approx. 360 m Winding seam pipe 1 x Drinking water distribution cold and warm 1 x Hygiene system 39 x Sanitary ware 17 x Radiators Approx. 830 m² Underfloor heating 2 x Heat pump 1 x Ventilation unit for 12,000 m3/h Start of work: November 2022 Duration of work: 220 working days