Earthworks, concrete, masonry, pipe-laying and road construction works
- approx. 4,500 m³ excavated soil
- Processing of approx. 1,900 m³ of concrete and 180 tons of structural steel
- Production of approx. 1,300 m² of masonry
- Laying of approx. 2,600 m of PE and PP pipelines DN 50 - DN 500
incl. pipe trenches
- Laying and paving of a total of approx. 3,800 m² of pavement and asphalt
- approx. 150 m² concrete surface renovation in the sand trap
Earthworks, concrete, masonry, pipe-laying and road construction works
- approx. 4,500 m³ excavated soil
- Processing of approx. 1,900 m³ of concrete and 180 tons of structural steel
- Production of approx. 1,300 m² of masonry
- Laying of approx. 2,600 m of PE and PP pipelines DN 50 - DN 500
incl. pipe trenches
- Laying and paving of a total of approx. 3,800 m² of pavement and asphalt
- approx. 150 m² concrete surface renovation in the sand trap