The subject of the contract is the execution of construction works consisting in the reconstruction of the technological installation and compressed air in the filter building at the Mokry Dwór Water Production Plant.
1. The subject of the contract is the execution of construction works consisting in the reconstruction of the technological installation and compressed air in the filter building at the Mokry Dwór Water Production Plant.
2. Detailed requirements of the Ordering Party regarding the subject of the contract are included in the Description of the subject of the contract, constituting Annex 1 to the SWZ, i.e. in the project documentation, which includes:
2.1. Detail Engineering for the Reconstruction of the technological installation and compressed air installation in the filter building at the Mokry Dwór Water Production Plant, developed by Proinvest sp. z o.o., date December 2022, sanitary, construction and construction industry
2.2. Detail Engineering for the Reconstruction of the technological installation and compressed air installation in the filter building at the Mokry Dwór Water Production Plant, developed by Proinvest sp. z o.o., date February 2023, electrical industry
2.3. Detail Engineering for the Reconstruction of the technological installation and compressed air installation in the filter building at the Mokry Dwór Water Production Plant, developed by Proinvest sp. z o.o., date January 2023, I&C industry
2.4. Technical specification of execution and acceptance of construction works, general requirements for the reconstruction of the technological installation and compressed air installation in the filter building at the Mokry Dwór Water Production Plant, developed by Proinvest sp. z o.o., date December 2022,
2.5. Technical specification of execution and acceptance of construction works for the reconstruction of the technological installation and compressed air installation in the filter building at the Mokry Dwór Water Production Plant, developed by Proinvest sp. z o.o., date December 2022, sanitary industry
2.6. Technical specification of execution and acceptance of construction works for the reconstruction of the technological installation and compressed air installation in the filter building at the Mokry Dwór Water Production Plant, developed by Proinvest sp. z o.o., date December 2022, construction and construction industry
2.7. Technical specification of execution and acceptance of construction works for the reconstruction of the technological installation and compressed air installation in the filter building at the Mokry Dwór Water Production Plant, developed by Proinvest sp. z o.o., date January 2023, electrical industry and I&C
2.8. Safety and health information for the reconstruction of the technological installation and compressed air installation in the filter building at the Mokry Dwór Water Production Plant, developed by Proinvest sp. z o.o., date December 2022,
3. The contracting authority shall enable a site inspection of the construction site. To do this, please contact Mr. Szczepan Polus, The on-site inspection is not mandatory.