Transformers | Tenderlake

Transformers

Contract Value:
-
Notice Type:
Contract Notice
Published Date:
21 March 2023
Closing Date:
31 March 2023
Location(s):
FI1B1 Helsinki-Uusimaa (FI Finland/SUOMI / FINLAND)
Description:
EU NOTIFICATION Procurement of the main transformers of Helen Electricity Network Ltd's Kruununhaka substation

Helen Sähköverkko Oy (later the Client) will build a 110/10 kV substation (abbreviated as Kr) in Kruununhaka, Helsinki. The new substation will replace the old substation in the adjacent building. The commissioning will take place in stages, and the substation and all its equipment are planned to be in use by 12/2025.

This purchase comprises the purchase of two (2) 110/10 kV 31,5 MVA OFWF cooled main transformers with auxiliary equipment and cooling systems for the substation in question, delivered, scraped, installed, tested and put into service in accordance with this contract notice and the subsequent invitation to tender and its annexes.

The procurement procedure shall be negotiated procedure. Tenders will be requested from those suppliers who, on the basis of requests to participate, will be selected as tenderers.

Before submitting a tender, each successful supplier candidate must visit the site on the spot.

The object of the acquisition is further detailed in the preliminary call for tender with attachments.

This purchase comprises the purchase of two (2) 110/10 kV 31,5 MVA OFWF cooled main transformers with auxiliary equipment and cooling systems for the substation in question, delivered, scraped, installed, tested and put into service in accordance with this contract notice and the subsequent invitation to tender and its annexes.

Transformers are placed in transformer rooms adjacent to the substation building. Radiators with cooling circuits are installed in the refrigeration equipment room adjacent to the transformer premises. The preliminary plans for the cooling system are attached to the invitation to tender.

The purchase of the transformer also includes 110 kV surge protectors with 8 installation bases installed in place. Connecting surge protectors to 110 kV currents is not included in the purchase of a transformer, but in the delivery of process equipment.

The procurement procedure shall be negotiated procedure. Tenders will be requested from those suppliers who, on the basis of requests to participate, will be selected as tenderers.

Before submitting a tender, each successful supplier candidate must visit the site on the spot.

The object of the acquisition is further detailed in the preliminary call for tender with attachments.

The transformer shall be delivered in full working order in accordance with the technical specifications, including its accessories and accessories.

Provisional timetable:

The transformers and their cooling systems can be commissioned on 11/2025 (preliminary fine deadline).

Download full details as .pdf
The Buyer:
Helen Sähköverkko Oy
CPV Code(s):
31170000 - Transformers