In the city of Nuremberg, the 110 kV SK143 line will be renewed in the coming years. The overall project with a length of approx. 4200 m is divided into several project parts or construction lots, the processing of which extends over several years. This tender includes Project Part 4 with 2 construction lots for the end of 2022/beginning of 2023.Services: Civil engineering work and laying of high-voltage cable ducts in open construction, co-laying of pipe trains. The refilling of the construction trenches and pits is carried out using liquid soil technology (use of liquid soil).
Building lot 1Civil engineering work and installation of high-voltage cable pipes as well as open pipe runs, route length approx. 540 m
Planned material requirements (medium):
2 x PP-HM empty pipe system 3x d200x7.7:6 pipes of 540 m length, material delivery including pipe sleeves, pipe bends, sealing caps
HDPE spacer for pipes 6x d200 and 2x d110:350 pieces, material delivery according to specifications drawing 1
HDPE spacer for pipes 3x d200 and 1x d110:24 pieces, material delivery according to specifications drawing 2
2 x PVC pipe run PVC d110x3.2:2 pipes of 520 m length material delivery including connections
Lot 2Division into 2 construction phases:
Civil engineering work and laying of high-voltage cable pipes and pipe runs in open design, route length BA1 approx. 300 m, BA2 route length approx. 330 m
Planned material requirements (medium):
2 x PP-HM empty pipe system 3x d200x7.7:6 pipes of 630 m length material delivery including pipe sleeves, pipe bends, sealing caps
HDPE spacer for pipes 6x d200 and 2x d110:410 pieces Material delivery according to specifications Drawing 1
HDPE spacers for pipes 3x d200 and 1x d110:20 pieces, material delivery according to specifications drawing 2
2 x PVC pipe run PVC d110x3.2:2 pipes of 630 m length, material delivery including connections