New construction of the Lichtbergschule Eiterfeld, school building N1-N5 - Sanitary work
New building Lichtbergschule N1-N5 - Description of the measures LV Sanitär
In the course of the project "New construction of the Lichtberg School in Eiterfeld", the sanitary facilities of the newly constructed school building of the Lichtberg School will be rebuilt.
The installation of the pipelines of the sewage and water systems is mainly carried out in the suspended ceiling or in lightweight walls. The installation in the technical rooms is carried out as surface-mounted installation.
Plastic pipes made of PP are provided for the drainage systems.
For the drinking water systems, pipes and fittings in stainless steel, as well as fittings made of gunmetal are provided.
Installation of plumbing objects is carried out on installation elements for metal stud walls or pre-wall mounting.
For the insulation of the drinking water pipes, aluminium-laminated insulating shells made of mineral wool are provided.
The rainwater pipes are insulated with diffusion-tight rubber.
Domestic hot water is prepared decentrally by means of instantaneous water heaters.
To supply the kitchen areas with softened water, a softening system is provided in the technical room.
The sanitary objects are made of sanitary porcelain.
The following service areas are included:
• Schmutzwasseranlagen
• Regenwasseranlagen
• Trinkwasseranlagen
Leistungsumfänge:
• Approx. 320 m of dirty water pipes DN 50 - 125 plus fittings
• Approx. 40 m dirty water pipes for greasy waste water DN 50 - 100 plus fittings
• Approx. 7 pieces of extension and attachment pieces for floor drains
• Approx. 20 m dirty water pipes for condensate DN 25 plus fittings
• Approx. 5 pcs pipe trace heating for outdoor sewage pipes
• approx. 290 m rainwater pipes DN 100 - 150 plus fittings incl. insulation
• approx. 1000 m drinking water pipes DN 15 - 50 plus fittings incl. insulation
• Approx. 70 pcs vortex shut-off valves
• Approx. 13 flow dividers
• Approx. 5 hygienic rinsing stations
• 1 piece water softener
• Approx. 55 pcs. instantaneous water heater
• approx. 40 toilet facilities
• Approx. 40 washbasin systems
• Approx. 40 electric hand dryers
• approx. 3 toilet facilities barrier-free
• approx. 3 washbasin systems barrier-free
• approx. 2 pcs. sink systems
• Fabrication of openings and core drilling, solid and lightweight walls