New construction of a pressure line, sewage treatment plant Nieder-Gemünden:
Performance picture Technical equipment according to § 55 HOAI (2013) Machine technology LP 1 to 8, commissioning in stages, equipment groups 1 and 3.
Planning services for the construction of a waste water pressure line with pumping station from the sewage treatment plant Nieder-Gemünden to the district sewage treatment plant Nieder-Ohmen.
Performance picture Technical equipment according to § 55 HOAI (2013) Maschinentechnik
LP 1 to 8, commissioning gradually. Asset groups 1 and 3.
The costs of the overall measure amount to approx. 2 510,000 EUR net (KG 300 + 400) due to a cost estimate.
The municipal sewage treatment plant in the district Nieder-Gemünden no longer meets the technical requirements for wastewater disposal and should be shut down. It is planned to build a waste water pressure line with pumping station to connect the wastewater treatment plant Nieder-Gemünden with the district sewage treatment plant Nieder-Ohmen. The pressure line is about 4.1 km long. At the lowest point (about 215 m above sea level) at the wastewater treatment plant Nieder-Gemünden, the pumping station is planned. The highest point (245 m above sea level) is located at the end of the pressure line, at the inlet to the district sewage treatment plant Nieder-Ohmen. The planned route has 5 high and 4 low points.
The client reserves special services as required. there is no entitlement to commission.