Description:
Heat Strategy 2020 – 2nd expansion stage Lot 6 - Modernisation of gas turbine 1

The gas turbine plant went into continuous operation for the first time in 1996 and has been modernized several times over the years.

The gas turbine plant of the CHP "Helmshäger Berg" consisted of three gas turbines, each with a waste heat boiler and separate exhaust gas ducts. Two of the three gas turbines have already been dismantled in the course of the construction of the Boddenluft CHP. The remaining gas turbine is to be modernized in accordance with the KWKG. According to §2 No. 18 KWKG, modernized CHP plants are those CHP plants in which essential plant components that determine efficiency have been renewed and the modernization results in an increase in efficiency. This includes, for example, the gas turbine (power and working turbine) itself as well as system components such as heat exchangers, waste heat boilers, pipe insulation or frequency converters, but not the building envelope or the sound insulation hood of the gas turbine.

The following components are part of the modernization:

Turbine

Compressor

Combustion chamber

Transmission

Luftfiltersystem

Schalldämmhaube

generator

Exhaust gas sound attenuation

Modification of the exhaust duct

Druckluftversorgungsanlage

Abhitzekessel

Wärmeauskopplung

Download full details as .pdf
The Buyer:
Stadtwerke Greifswald GmbH
CPV Code(s):
42100000 - Machinery for the production and use of mechanical power
42112300 - Gas turbines
45350000 - Mechanical installations