Project Title; Nixons Corner, Derry.
Construction; 8 no dwellings.
End User; General Needs.
Mix; 2 no 5p 3b houses and 6 no 3p 2b houses.
Estimated Construction Cost; 643 067 GBP.
Estimated/Anticipated Start On Site; March 2015.
Estimated/Anticipated Completion; March 2016.
Estimated Construction Period; 12 months.
Contract; NEC Short Form.