L1 Road construction work for the construction of a pavement including preparatory demolition work
L2 Gardening and landscaping work for the production of roadside greenery
Lot 1 Road worksLot 1 Road works
Road construction work for the construction of a pavement including preparatory demolition work
Remove and dispose of 275 m² of bituminous pavement
460 m² of artificial stone slabs and partly dispose of or partly dispose of. store for replacement
Loosening, storing and disposing of 700 m³ of soil
75 m3 of antifreeze gravel supply, install
Produce 355 m² frost protection layer
Remove 165 m from the B6 curb and partly remove the B6 curb. dispose of or partly dispose of. store for replacement
Install 470m³ substrate type A
Install 10 m³ substrate type B
310 m install curb B6
Installing 310 m² of asphalt base and surface courses
205 m² of artificial stone slab flooring
Lot 2 Gardening and landscaping work for the production of roadside greeneryLot 2
Gardening and landscaping work for the production of roadside greenery.
45 m tree protection bar, incl. install foundation
Plant 15 trees StU 30/35
84 shrub plantings
85 m3 topsoil supply, install
Produce 210 m2 of vegetation base course
1 year of completion care
2 years of development maintenance