Turnerschaft Jahn München v. 1887 e.V. / VE 02 - Elektroarbeiten
This contract is for the renovation of the existing sports facility of the Turnerschaft München by
1887 e.V. from 1971. This is the second construction phase of an overall project,
the first construction phase, which has already been completed (new construction of an independent gymnasium)
preceded it. In the following, therefore, there will be more talk of the second construction phase (BA2 for short).
The existing sports complex includes two gymnasiums ("Small Hall" and "Great Hall") as well as a
intermediate central wing with changing rooms and sanitary facilities and additional administrative rooms. In
Demolition work is already carried out prior to the actual installation work (not scope of this order)
Carried out.
The renovation is to be carried out in two phases:
The subsection BA2.1 mainly comprises the renovation and extension of the "small hall" as well as the renovation of a
WC core and minor renovation work of the administration rooms.
The subsection BA2.2 includes the renovation of the "Great Hall" as well as the directly located smaller
Sports rooms "judo room" and "multipurpose room".
The two construction phases will be separated in time and worked on one after the other. The unprocessed areas
are to remain in operation during the other construction phase. The interfaces here are always
to coordinate closely with the construction management so that sports operations are disturbed as little as possible.
The property is located at Weltenburger Str. 53, 81677 Munich.
All services of the electrical contract are to be carried out one after the other in subsections BA2.1 and 2.2.
The property is located at Weltenburger Str. 53, 81677 Munich.
The main power supply, video surveillance, BMA and Zuko were renewed in Ba 1 and the new systems
in Ba 2 are to be connected to it. The connecting cables for this are already in the electrical room Ba 2.