B 27, Gumpenbach Bridge Kornwestheim - replacement building.
The construction project includes the replacement of the Gumpenbach Bridge, which consists of two separate substructures, as well as the renovation of the noise protection walls. A substructure of the semi-integral bridge structure is produced in a lateral position and then transversely shifted into the final position.
In addition, as part of the construction project, the section of track in front of and behind the bridge structure will be renewed over a length of approx. 470 m, plus the loading and unloading ramps at Kornwestheim-Nord.
The existing sewage system (collecting pipes and road drainage) will be in
This section completely rebuilt. The existing channels were largely dismantled.
The measure will be carried out throughout the construction period while maintaining the
Traffic performed