The new building of the sports hall will be built on the area of the previous sports field at the school between the school building and Waldschmidtstraße.
The building is predominantly a reinforced concrete structure with EIFS. The roof of the sports hall is hipped. The
Roof construction is designed as an explosive device with wooden trusses and steel tension struts. Buildings for
changing rooms, plumbing, technology, equipment and gallery with a green flat roof.
Exterior building dimensions: approx. 38 x 45 m
Building height: approx. 14 m
masses:
ca. 400 m2 Prallwand
1 Regieraumfenster
6 Geräteraumtore
3 single-leaf doors
2 double-leaf doors
4 niches for wall bars
2 niches for climbing poles
approx. 5 cover doors for dew protection
approx. 2 installation boxes for switches
Events:
Ausführungszeitraum: 25.01.2023 – 08.08.2023
W+M planning:25.01.2023 – 15.02.2023
Impact wall UK with doors & windows, installation without base & soffits (incl. insertion work by ELT) 23.03.2023 - 12.05.2023
Impact wall mounting bases and soffits 02.08.2023 – 08.08.2023