Marine construction works | Tenderlake

Marine construction works

Contract Value:
-
Notice Type:
Contract award notice – utilities
Published Date:
08 September 2023
Closing Date:
Location(s):
DK02 Sjælland (DK Denmark/DANMARK)
Description:
Gravity Based Foundations for Aflandshage Wind Farm

HOFOR is establishing an offshore wind farm (Aflandshage Wind Farm) in Øresund in the area between Stevns and Amager's southern tip. The wind farm is expected to have a capacity of 300 MW corresponding to 26 turbines. This contract award notice concerns the EPCI contract regarding gravity based foundations. The tender procedure has been carried out as a negotiated procedure using the qualification system Achilles UNCE.

Aflandshage Wind Farm is to be situated in Øresund, the area between Stevns and Amager's southern tip and is expected to have a maximum capacity of 300 MW, corresponding to 26 turbines. The Aflandshage Wind Farm will most likely be connected to the grid through Energinet's existing 132 kV station at Avedøreværket.

The tender covered by this contract award notice concern the procurement of gravity based foundations, including engineering, investigations, design, manufacture, procurement, construction, transportation, installation, erection, completion and testing of the foundations for the Aflandshage Wind Farm.

Awarded to:
Wind Turbine Generators for Aflandshage Wind Farm
Per Aarsleff A/S, Viby J (DK)
Download full details as .pdf
The Buyer:
HOFOR Vind A/S
CPV Code(s):
31121340 - Wind farm
45244000 - Marine construction works
45251160 - Wind-power installation works
71325000 - Foundation-design services