- 150 kW gas boiler room - Distribution of radiators and underfloor heating - Air handling units for the nursery and the reheating kitchen - Ventilation ducts, fire dampers and accessories - Domestic hot water production - Sanitary appliances - Cold water, hot water and circulation distribution - Wastewater and soiled water drainage networks Start of work: October 2024 Duration of the work: 250 O.J. (in several phases)
- 150 kW gas boiler room - Distribution of radiators and underfloor heating - Air handling units for the nursery and the reheating kitchen - Ventilation ducts, fire dampers and accessories - Domestic hot water production - Sanitary appliances - Cold water, hot water and circulation distribution - Wastewater and soiled water drainage networks Start of work: October 2024 Duration of the work: 250 O.J. (in several phases)