The following services are to be provided by the contractor:
- FO splice planning (backbone and FTTB) based on the implementation planning of the infrastructure, interconnection of the MFGs and RVts, as well as connection of the new house connections,
- Documentation of all components (from the POP to the end customer's APL) of the built FTTX routes,
- Setting up of tube distributors approx. 200 pieces,
- Procurement and delivery of the components
—— MFG18 incl. Base and ground spike,
- assembly material,
- If required LSA + strips,
—— ODF distributor,
—— FO splice and patch assemblies,
—— external meter column;
- Pre-assembly of the MFG18, approx. 80 pieces,
- Setting up the MFG18 including passive technology, approx. 80 pieces.
The project area encompasses 53 cities and municipalities in the Rhein-Neckar district.
Approx. 200 fiber optic tube distributors based on a fiber optic distributor UNI 6 housing with a standard configuration of 4 x 12 microtubes are used.
The MFG locations are secured and specified by the high-speed network Rhein-Neckar (ZV).
The MFG-18 are planned as pure fiber optic locations (max. 550 buildings per MFG with fiber optic connection). If required, the MFG-18s are to be provided as hybrid locations (max. 350 buildings per MFG with fiber optic cables.
Connection and up to 2x 100DA CU cables to KvZ).