Construction power supply during the entire construction period, including structural work
Construction power supply during the entire construction period, including structural work
(not for special foundation engineering)
Construction of the construction power supply in two successive parts.
Part 1: Setting up main group distributors including meters and laying the supply lines
Transformer station for the supply of the shell construction measures
Part 2: Expanding the construction power system. Construction of further construction site power distributors in the individual
Levels of component Azur supply of the trades for the interior fittings. In component B UG
A construction site power distributor will also be built at the ELT technical centre.