- St. Marien and Annastift Hospital,
- Human + Health future project,
- Extension of component G and conversion of component F,
- Trade VE_470 medical gases.
New building component G:
- 15 area control units for 2 to 4 compressed gases or vacuum,
- approx. 155 UP withdrawal points for med. Gases and vacuum,
- approx. 25 connections to on-site med. Rails and DVE,
- approx. 140 withdrawal points for med. Rails and DVE (delivery only),
- approx. 4 850 m cables for med. Gases, vacuum and AGFS made of copper DN 6-DN 50.
Reconstruction / extension of component F:
- 4 area control units for 3 to 4 pressurized gases or vacuum,
- approx. 25 UP withdrawal points for med. Gases and vacuum,
- approx. 25 connections to on-site med. Rails and DVE,
- approx. 245 withdrawal points for med. Rails and DVE (delivery only),
- Dismantling of approx. 500 m of copper pipelines DN 6-DN 25,
- approx. 900 m lines for med. Gases and vacuum made of copper DN 6-DN 32.
Expected execution from week 20/2021 to week 04/2023.