The Fritz Ulrich School, a 3-class community school with approx. 450 pupils, will be expanded for full-day operation, expanded barrier-free and renovated.
The school consists of 2 building blocks from 1965, offset by 1.86 m from each other, which are connected by 3 stairwells in split-level construction and another one-storey, raised structure built in 2008 with connection via 2 bridges.
As an extension, the inner courtyards between the stairwells are covered and used as areas for all-day use (cafeteria / theater workshop).
The building blocks are accessible with new galleries in the atria and a new elevator system.
The measure includes the constructive and safety-related fire protection renovation. The construction work will be carried out in 3 phases during operation from summer 2020 to 2022.
Building data: GFA approx. 7 050 m
Metal construction locksmith interior doors:
- T30 RS steel doors, 1-leaf, approx. 12 pieces;
- Pipe frame door system as a frame glass system 1-leaf. T30 RS, 1 piece;
- Pipe frame door system as a frame glass system 1-leaf. T30 RS, 2 pieces;
- Pipe frame door system as a frame glass system 2-leaf. T30 RS, 3 pieces;
- Pipe frame door system as a frame glass system 2-leaf. T30 RS, 5 pieces;
- Pipe frame door system as a frame glass system 2-leaf. T30 RS, 3 pieces;
- Pipe frame door system as a frame glass system 1-leaf. T30 RS;
- Pipe frame door system as a frame glass system 1-leaf. T30 RS;
- Door closers, door stops, door fittings.