The subject of the contract is the implementation of the task entitled Construction of networks, connections and substations consisting in the reconstruction of the power supply system from the group substation at Smętka 5 Street, i.e. the execution of construction works consisting in the replacement of existing heat networks made in the traditional system with a heat network in the technology of pre-insulated pipes in Olsztyn and the construction of compact heat substations with assembly, from the Contractor's materials as part of the project entitled "Reducing the emissivity of the economy by improving the efficiency of heat distribution in Olsztyn as a result of the reconstruction of the heating network and nodes – stage III".
A detailed description of the subject of the contract specifies:
Appendix 1.1 – Land development project at Smętka Street
Appendix 1.2 – Technical design of the Smętka Street network
Appendix 1.3 – Construction project of the substation grunwaldzka 7a
Appendix 1.4 – Construction project of the substation at 9 Grunwaldzka Street
Annex 2.1 – Bill of quantities of connections smętka street
Appendix 2.2 – Bill of quantities of the substation grunwaldzka 7a
Appendix 2.3 – Bill of quantities of the substation grunwaldzka 9
Appendix 3 – Technical Specification for the Execution and Acceptance of Works
The scope of the order:
a) Construction and assembly works:
• dismantling and demolition work,
• earthworks,
• purchase, delivery and installation of fittings, pipelines,
• landscaping and ordering of the land,
• construction of thermal networks,
• construction of compact substations, their assembly and commissioning,
• Reception required.
b) Execution of surveying inventory and as-built documentation.
In addition, the Contractor is obliged on its own and at its own expense
in particular, to:
• implementation of the BIOZ plan,
• site occupation, including road lanes and payment of related charges,
• notification of property managers of the planned time limit for carrying out the work,
• preparation of the site for construction along with its marking and cutting down of trees to be removed,
• development of a road traffic organization project and its implementation,
• safeguarding the construction site against third party access,
• ensuring the operation of surveying investments,
• solving the question of water and electricity consumption,
• restoring the area and surface to its previous state, confirmed by a protocol signed by the manager or owner of the site
• delivery, assembly and commissioning of substations made on the basis of projects attached to the SWZ,
• electrical installation for the needs of the node along with as-built measurements,
• development of user manuals, technological diagrams of nodes and placing them in the node rooms,
• civil liability insurance to the extent specified in the draft contract (constituting Annex 4 to the SWZ),
• making notifications and acceptances of devices by the UDT, if required,
• construction insurance against damage likely to occur and from sudden, random events and civil liability works, equipment and construction equipment,
• exportation of debris and other demolition materials, together with waste disposal.
The subject of the contract is the implementation of the task entitled Construction of networks, connections and substations consisting in the reconstruction of the power supply system from the group substation at Smętka 5 Street, i.e. the execution of construction works consisting in the replacement of existing heat networks made in the traditional system with a heat network in the technology of pre-insulated pipes in Olsztyn and the construction of compact heat substations with assembly, from the Contractor's materials as part of the project entitled "Reducing the emissivity of the economy by improving the efficiency of heat distribution in Olsztyn as a result of the reconstruction of the heating network and nodes – stage III".