Rear-ventilated façade with metal substructure and fibre core panels in 2 construction phases
1st construction phase: School building
2nd construction phase: external elevator
Execution periods:
-Planning/ workshop drawings directly after placing the order - expected mid/end of December 2024
-Assembly 1st phase: expected 05.02.24 to 30.05.24
-Assembly 2nd phase: expected 05.08.24 to 07.09.24
Quantities:
1st construction building: approx. 1,170 m² rear-ventilated façade
2nd construction building: approx. 150 m² external elevator